MIDLAKE AND SOUTHLAKE ORTHOPEDIC SPINE CENTERS

  • Locations: Midlake Campus, Gary | Southlake Campus, Merrillville
  • Completed: November 2014
  • Delivery method: General contractor

Powers & Sons reconfigured and converted existing space at Methodist Hospitals’ Midlake and Southlake northwestern Indiana campuses into Orthopedic Spine Centers.

The Powers team built the original Midlake campus in 2004; its new Midlake Orthopedic Spine Center is 6,000 SF and was completed in 72 days.

The new Southlake center is 8,000 SF and was completed in 54 days. As designed, the project was over-budget. Powers & Sons provided value-added engineering alternatives to the owner, design team, and subcontractors, reducing the cost and bringing both projects in under budget.